Canyon Classroom Replacement Project

Rendering of the completed campus showing the new two story classroom building, the restored 1894 School House and children on the assembly area.
The new two story classroom building and the restored 1894 School House, seen from the assembly area. Rendering from the LAUSD project materials.

Canyon Charter Elementary is in the middle of a multi-year classroom replacement project planned, funded, and managed by the Los Angeles Unified School District. The district is replacing the portable classrooms that have served our campus for decades with a permanent two story building, and rebuilding the grounds, parking, and playground around it.

Project History and Approvals

In November 2017, the LAUSD Board of Education approved the replacement of portable classrooms across the district, including Canyon. Funding for the Canyon project was approved in November 2021. The plans were reviewed and approved by the district and by the California Coastal Commission. Construction began in January 2024.

Rendering of the new front entrance from Entrada Drive with a lawn, flagpole and vertical wood screen carrying the school name.
The new front entrance and the grass field along Entrada Drive. Rendering from the LAUSD project materials.

The New Classroom Building

  • Two stories, roughly 17,800 square feet
  • Nine classrooms
  • Science space and additional support spaces
  • A designated special education room
  • Relocation and restoration of our historic 1894 School House
Rendering of the new two story classroom building across a new grass field, with a jacaranda in bloom.
The new building across the grass field that replaces part of the current construction area. Rendering from the LAUSD project materials.

At the community meeting held on June 16, 2026, LAUSD described the nine rooms as three kindergarten classrooms and six general classrooms. At the August 2026 Booster meeting, Principal Sheard described the grade placement as kindergarten on the lower floor and fourth and fifth grade on the upper floor.

Campus Site Improvements

Alongside the new building, the project covers work across the rest of the campus:

  • Removal of the remaining portable classrooms and the existing kindergarten building
  • Rerouting of a sewer line beneath the campus
  • Technology network and fire alarm upgrades
  • ADA improvements, including accessible ramps, railings, and parking
  • A new playground with a cool surface coating
  • New landscaping, hardscape, irrigation, and expanded staff parking

Trees

Street level rendering of the new classroom building showing its wood clad upper floor, sloping roof and concrete retaining wall.
The new building from street level. Rendering from the LAUSD project materials.

The landscaping plan removes three eucalyptus and one jacaranda. LAUSD stated at the June 2026 community meeting that the total number of trees on site will increase by 20 by the end of construction, to 86.

Project Cost and Funding

LAUSD has put the total project cost at $57.5 million. The project is funded and managed entirely by the district. No Booster Club funds and no family donations go toward the construction.

Proposed site plan labeling the new building, relocated library, kinder garden, multi purpose room, administration, existing classrooms, playground and school entrance.
Proposed site plan for the finished campus. Source: LAUSD community meeting, June 16, 2026.

Five-Phase Construction Sequence

LAUSD presented a five phase sequence at the community meeting held on June 16, 2026.

Phase One covers the sewer line reroute along with interim classroom space and ADA ramps and railings. The interim classrooms and ADA work are finished. The sewer line required a redesign after crews encountered conditions that the original plan did not account for, and that portion is now scheduled for summer 2027.

LAUSD plan drawing for Phase 1.
Phase 1, first and second quarter of 2024. Source: LAUSD community meeting, June 16, 2026.

Phase Two covers the historic School House and the new two story building. The School House has been moved and connected to utilities, with a retaining wall alongside it. Construction of the new classroom building is underway.

LAUSD plan drawing for Phase 2a and 2b.
Phase 2a and 2b, first quarter of 2027. Source: LAUSD community meeting, June 16, 2026.

Phase Three brings demolition of the remaining classroom building, removal of the interim units, temporary staff parking, and the start of work on the playground.

LAUSD plan drawing for Phase 3.
Phase 3, second quarter of 2027. Source: LAUSD community meeting, June 16, 2026.

Phase Four brings demolition of the kindergarten building and completion of the new staff parking lot.

LAUSD plan drawing for Phase 4.
Phase 4, third quarter of 2027. Source: LAUSD community meeting, June 16, 2026.

Phase Five completes all hardscape, irrigation, and landscaping.

At the June 2026 meeting LAUSD gave a target quarter for each phase: the first half of 2024 for Phase One, the first quarter of 2027 for Phase Two, the second quarter for Phase Three, the third quarter for Phase Four, and the fourth quarter of 2027 for Phase Five. The plan drawings for each phase are below.

LAUSD plan drawing for Phase 5.
Phase 5, fourth quarter of 2027. Source: LAUSD community meeting, June 16, 2026.

Project Schedule and Completion Estimates

Below are the timing estimates given publicly for each milestone, along with the source of the estimate and the date it was given.

Milestone Estimate Source and date of that estimate
Historic School House back in use Complete, August 2026 LAUSD, community meeting, June 2026
New classroom building complete End of December 2026 Icon West, the general contractor, reported by Principal Sheard, August 2026
New classroom building complete Spring 2027 LAUSD, reported by Principal Sheard, August 2026
Students move into the new classroom building Before the start of the spring semester, early 2027 LAUSD, community meeting, June 2026
Phase Three begins, playground work starts Second quarter of 2027 LAUSD, community meeting, June 2026
Sewer line construction Summer 2027 LAUSD, community meeting, June 2026
Entire project complete Fourth quarter of 2027 LAUSD, community meeting, June 2026

LAUSD sets and revises this schedule, and the school has no role in it. The district's published estimates have moved over the course of the project, and this page is updated whenever the district issues a new one.

Rendering of the campus frontage along Entrada Drive with new sidewalk, planting and the entrance in the distance.
The Entrada Drive frontage. Rendering from the LAUSD project materials.

Classroom Relocation When the New Building Opens

The new building holds nine classrooms, and fifteen Canyon classrooms will change rooms when it opens. Kindergarten moves to the lower floor of the new building, and fourth and fifth grade move to the upper floor. Most of the remaining classes move into rooms 1 through 10, the permanent structures that stay in place for the rest of the project. Four classrooms stay where they are.

Principal Sheard is working through the relocation logistics with the district, and the timing depends on when LAUSD releases the building. We will share the move schedule, room assignments, and anything families need to do through the Chronicle and this page once the district confirms the move-in window.

Rendering of the rebuilt front parking lot with the school entrance sign beyond it.
The rebuilt front parking lot. Rendering from the LAUSD project materials.

Campus Changes That Follow the Move

Several parts of the project can only begin once classes are out of the current buildings. LAUSD and Principal Sheard have described the sequence in this order:

  1. Demolition of the kindergarten building
  2. Removal of the remaining portable classrooms
  3. A temporary parking lot along the Entrada Drive fence while the front lot is rebuilt
  4. Reconstruction of the front parking lot, which changes orientation and moves to roughly where the kindergarten building stands today
  5. A new front entrance with a walkway leading up to it
  6. The full playground, including a grass field running along the front of the new building

The temporary lot takes some playground space while it is in use, and less than the construction footprint takes today. Once the front entrance is finished, families and visitors will have a clearly marked path from the street to the school office.

The 1894 School House

Our School House has been the heart of this campus since 1894, and it is the oldest school building still used by children anywhere in Los Angeles County. It has been moved several times across its history, most recently in 1997 and again as part of this project.

Elevated rendering showing the relocated 1894 School House at the corner of the campus with the ocean beyond.
The School House in its new position at the corner of the campus. Rendering from the LAUSD project materials.

Moving and restoring the School House was one of the first major pieces of the work, and it was sequenced early so that playground space could open back up for students. The building was relocated, connected to utilities, and given a retaining wall alongside it. It received a round of care and upgrades over the summer of 2026, including a restored bell in the belfry that rings again. Completing this phase also opened additional playground area and a new outdoor reading space.

Current Work and Daily Campus Impact

Most of the work underway is interior. Recent weekly reports have listed drywall, painting, electrical, window waterproofing, restroom tile, and the concrete block site wall. Between 36 and 50 workers have been on site on a typical day this fall, and nearly all of them are inside the building, which is why the site can look quiet from the street.

Aerial rendering of the completed Canyon campus within the surrounding neighborhood.
The completed campus from above. Rendering from the LAUSD project materials.

The contractor issues a written update every Friday. Principal Sheard includes it in the Chronicle each Sunday, and this page is updated as the district revises the scope or the schedule.

Project Contacts and Where to Send Questions

Construction questions go to LAUSD rather than to the school office, since the district manages the project directly and holds the schedule.

Maribel Serrano, LAUSD Community Relations, (213) 241-2258, cp-maribel-serrano@lausd.net. Ms. Serrano handles the detailed logistical questions about the project and can add you to the project notification list. Her contact information also appears on the LAUSD construction flyers sent to families.

Facilities Services Division, Community Relations, (213) 241-1340, lausd.org/facilities/community-relations

For general questions, and for anything covered in the Chronicle, please contact Principal Nicole Sheard. For anything about your child's school day, reach the Canyon office at 310.454.7510.

🎉 Party Book 🎉

This year’s Party Book is live. Dinners, outings, crafts and celebrations hosted by Canyon families, on sale now.

Party Book parties are live

See the Parties

Spots are first come, first served.

Upcoming Tours 2026-2027

We would love to show you around Canyon. Tour dates for 2026-27:

• Thu, November 19, 2026
• Tue, December 15, 2026
• Thu, January 21, 2027
• Thu, February 25, 2027

Sign Up for a Tour

Tours begin promptly at 9:00am and run until 10:30am.

Annual Giving

Your tax deductible donation to our Canyon Booster Annual Giving Campaign funds classroom aides, smaller class sizes, PE, digital learning, art, drama, music and so much more.

Donate Today!

Thank you for making our community a beneficiary of your philanthropy.